Exam Code: H12-425_V2.0-ENU
Exam Name: HCIP-Data Center Facility Deployment V2.0
Available Language: English
Exam Cost: $
HCIP-Data Center Facility Deployment V2.0 Is The Professional Level Certification
Huawei HCIP-Data Center Facility Deployment certification is the professional level, the current version is V2.0. It requires to pass H12-425_V2.0-ENU exam successfully. Earning HCIP-Data Center Facility Deployment V2.0 certification proves that you will be able to have a basic command of Huawei modular data center solution, power distribution system solution, cooling system solution, and monitoring system solution, and be able to work as a pre-sales engineer, deployment and commissioning engineer, and solution engineer for data center infrastructure.
Examkingdom Huawei H12-425_V2.0 Exam pdf,
Best Huawei H12-425_V2.0 Downloads, Huawei H12-425_V2.0 Dumps at Certkingdom.com
HCIP-Data Center Facility Deployment V2.0 H12-425_V2.0-ENU Exam Outline
The HCIP-Data Center Facility Deployment V2.0 mainly focuses on product technical features, installation and deployment, and parameter configuration, the product series includes the following products: Huawei modular data center Fusion Module series products, Huawei UPS and precision PDC series products, Huawei data center energy storage products, Huawei data center smart cooling products, and Huawei data center DCIM system products. Candidates need to be familiar with Huawei modular data center solution, power distribution system solution, cooling system solution, and monitoring system solution.
1. Introduction to Huawei Data Center Infrastructure 2%
2. Introduction to Modular Data Center Solution FusionModule2000 and 5000 5%
3. Introduction to Prefabricated All-in-One Data Center Solution FusionDC1000 3%
4. Introduction to Smart Mini and Small Data Center Solution FusionModule500 and 800 3%
5. Integrated UPS Introduction 3%
6. FusionModule2000 Installation 5%
7. Application of VRLA Batteries 3%
8. Huawei SmartLi Introduction, Installation, and Commissioning 3%
9. UPS2000 Product Introduction 3%
10. UPS2000 Installation 2%
11. UPS2000 LCD Operations and Commissioning 3%
12. UPS5000 Product Introduction 7%
13. UPS5000 Installation 2%
14. UPS5000 LCD Operations and Commissioning 8%
15. PDU8000 Modular PDF Introduction 3%
16. Introduction to Data Center Cooling Solutions 3%
17. Introduction to Huawei Air-Cooled Precision Air Conditioner 3%
18. Introduction to Huawei Chilled Water Precision Air Conditioners 3%
19. Introduction to the Huawei Modular Indirect Evaporative Cooling System 2%
20. NetCol5000-A042 Installation and Commissioning 9%
21. NetCol8000-C (070-260) Installation and Commissioning 3%
22. NetCol8000-E220 Installation and Commissioning 2%
23. ECC800-Pro Introduction 6%
24. Huawei DCIM Management Tool Introduction 6%
25. Huawei DCIM Product Introduction 8%
H12-425_V2.0-ENU exam for HCIP-Data Center Facility Deployment V2.0 certification exam is popular. If you are one of them and you are preparing for H12-425_V2.0-ENU exam, just come for the valid H12-425_V2.0-ENU exam questions to complete HCIP-Data Center Facility Deployment V2.0 certification successfully.
Sample Question and Answers
QUESTION 1
Which air supply mode requires reasonable raised floor height?
A. Air supply mode using blast caps.
B. Underfloor air supply mode
C. Air supply mode using wind pipe
D. In-row horizontal air supply mode
Answer: B
QUESTION 2
Which of the following statements is true about UPS5000 power modules and bypass modules?
A. The UPSS000-E-200K and UPS5000-E-400K use the same power module and provide the same capacity of 50 kVA but have different numbers of power modules.
B. For UPSs of the same model but in different power segments, their bypass module capacity is the same.
C. The power module capacity of both the UPS5000-S and UPS5000-E is 50 kVA. Therefore, the two types of UPS can be used together.
D. The power modules used in the UPSS000-S-1200K are the same as those used in the UPS5000-E- 200K.
Answer: A
QUESTION 3
In operant conditioning, the subject is free to make responses at any time, So conditioning is measured by the rate of responding. In most other Ways, however, their forms of learning are essentially the same.
A. When UPSs are connected in parallel, connect loads to the pL terminal.
B. When a single UPS works and loads are of the same importance, connect all loads to the sL terminal.
C. When a single UPS works and loads are divided into two levels, connect the primary load to the sL terminal and the secondary load to the pl_ terminal.
D. When the UPS is overloaded, the loads connected to the sL terminal will be powered off first to ensure continuous power supply to the loads connected to the pj_ terminal.
Answer: D
QUESTION 4
What is the input/output voltage range of the SmartLi BCU?
A. 280415 V
B. 300400 V
C. 300480 V
D. W00-544 V
Answer: C
QUESTION 5
To determine whether the R410A refrigerant meets requirements, compare the internal pressure of
the refrigerant with the saturation pressure corresponding to the refrigerant temperature. If the
difference between the internal pressure and the saturation pressure is within the range of which of
the following, replace the refrigerant?
A. 0-0.05 MPa
B. 0.05-0.1 MPa
C. 0.1-0.2 MPa
D. 0.25-0.3 MPa
Answer: B
QUESTION 6
Which of the following statements is false about the ECM of the UPS5000-E?
A. As a control interface for the entire system, the ECM communicates with each module and provides a bus for communication between the dry contact card and the system control card.
B. The ECM controls the bypass module to work properly, if one ECM is faulty, the UPS can still work in normal mode but cannot be manually switched to bypass mode.
C. The ECM ensures equalized output currents between modules so that load power is equally shared.
D. The ECM provides three types of CAN communication: monitoring CAN communication, intra-rack parallel CAN communication, and inter-rack parallel CAN communication.
Answer: B
Post your comments